Worthing’s former Aquarena site is barely recognisable as construction work on the new Bayside scheme continues…

The excavation process on the land in Brighton Road is nearing completion, as construction crews dig out the foundations and space for an underground car park.

Huge bearing piles are due to be installed by the end of May and the structural frame works will then follow in late June. This will take about 12 months.

Once Roffey Homes’ £45m transformation is complete, the seafront site will be home to more than 140 properties, a cafe and a commercial space.